Bethlehem Baptist Family Center


Return to Completed Projects

This project consisted of a 25,000 square foot addition to an existing site in Tacoma.  New facilities include classrooms, a gynasium, and locker rooms.
 


July 31, 2002 - Substantial Completion
 


May 3, 2002 - Gymnasium interior.
 


March 1st, 2002 - Roof framing and mechanical rough-in.
 
 


January 28, 2002 - Ridge beam up, framing ongoing.
 
 


January 28th, 2002 - Delivery of 87' gymnasium ridge beam.
 
 


November 26th, 2001 - Foundation walls are complete, preparing for slabs.
 


September 26, 2001 - Footings in progress