Champs II - Seattle, WA


  Return to Completed Projects

Architect: Gordon K. Walker

Champs II was an interior renovation for Champs Karting.  This project consisted of exterior improvements and interior renovations to an existing warehouse to transform it into an indoor electric high speed go-kart track.  The warehouse is 42,791 square feet, and provides a longer, wider track than their Redmond facility.  For more information about Champs Karting, you can visit their web site.
 


View from lobby into game room
 


February 22, 2002 - Just a few days before the grand opening
 
 


February 12, 2002 - Almost ready for City of Seattle final inspection
 


February 7, 2002 - Track being laid out.


January 29, 2002 - Owner testing for track layout, Interior finishes being applied
 
 


January 24, 2002 - Snack Bar / Sales Counter under construction
 
 


January 3, 2002 - Drywall being hung and taped as seen from track area.  Window frames being installed.
 
 


December 10, 2001 - Heating work started, insulation going up, and glu-laminated beams painted black.
 
 


November 26, 2001 - Partition walls almost complete
 
 


November 19, 2001  - Interior partition walls going up